Client: Costain / Hochtief J.V.
Value: £195,000.00
Works Package:
Construction of a new temporary platform to platform 10. The works consisted of pre-fabrication of 150m of platform tables utilising the Doka Framax panel system and the installation of the pre-fabricated platform units during a Christmas possession shutdown period of 60 hours consisting of two shift gangs of installers. The works were completed within 57 hours and the platform was successfully handed to Network Rail ahead of time.
Quantities:
- 150 m of Doka Framax Table Platforms pre-fabricated
- 150 m of Doka Framax Table Platforms installed within 57 hours – 3 Hours ahead of programme
- 150m of Tactile Paving laid.
- Christmas possession works carried out.